San Miguel Energy Corp. secured the regulator’s approval to supply power to an electric cooperative, helping ensure for the moment adequate and affordable supply in the Cagayan province.

In an order, the Energy Regulatory Commission (ERC) granted a provisional approval for the interim power supply agreement between Cagayan I Electric Cooperative Inc. (Cagelco I) and San Miguel Energy.

The ERC noted that an initial evaluation of the application showed that the agreement would “redound to the benefit of Cagelco I’s consumers in terms of continuous, reliable, efficient and affordable power supply as mandated by the Electric Power Industry Reform Act (Epira).”

Article continues after this advertisement

The offer of San Miguel Energy was reported to be the “most compliant,” having met the power supply requirements of Cagelco I up to Dec. 25, 2012, during which the interim agreement between the two parties will expire.

FEATURED STORIES

Also, a simulation showed that the blended generation rate of Cagelco I, if it were to include the supply from San Miguel Energy, would result in a reduction of rates by around 27 centavos per kilowatt-hour.

San Miguel Energy will be providing power to Cagelco from the 1,294-megawatt Sual coal-fired power plant in Pangasinan.

Article continues after this advertisement

The power firm is currently the independent power producer administrator (Ippa) of the Sual facility, which means that it is responsible for the management of the power plant’s contracted capacities and fuel supply.

Article continues after this advertisement

Cagelco I needs the additional supply from San Miguel Energy while it waits for GNPower Ltd. Co. to start operating its 600-MW coal-fired power plant in Mariveles, Bataan.

According to the ERC order, Cagelco I has an existing 15-year power supply agreement with GNPower that was already approved back in October 2007. GNPower was supposed to start operations last January, but unforeseen delays forced the power company to reset commercial operations to a later date.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Cagayan province, electricity distribution, Energy

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.