2 of 10 Aurora eco zone projects left undone near completion

2 of 10 Aurora eco zone projects left undone near completion

/ 09:23 AM July 22, 2024

2 of 10 Aurora eco zone projects left undone near completion

Photo from Aurora Pacific Economic Zone (APECO)/Facebook

MANILA — The Aurora Pacific Economic Zone and Freeport Authority (Apeco) will inaugurate this month two of 10 projects that were not finished by the past administration.

Apeco president and chief executive officer Gil Taway IV told the Philippine News Agency (PNA) that it will soon finish construction of the P27-million Fire Station Project and the P28-million Sewage Treatment Plant Project Phase 1.

Article continues after this advertisement

The P60-million Central Water Project Phase 1 will be finished next as the project is around 60 to 70 percent complete, the Apeco chief said.

FEATURED STORIES

READ: Apeco rebidding stalled projects worth nearly P800M

“This is very timely after the visit of President (Ferdinand R.) Marcos (Jr.) in Aurora,” Taway said in a recent interview. “We are fast-tracking all of these projects.”

Article continues after this advertisement

Earlier, Taway shared to PNA that there are 10 projects in Apeco amounting to P796 million that were left unfinished by the past administration.

Article continues after this advertisement

He said some of the contracts of these projects were terminated and offered for rebidding.

Article continues after this advertisement

During his visit to Baler last July 12, Marcos vowed to continue the unfinished projects.

“One of the issues we are finding a solution for is the abandoned Apeco projects worth about P800 million,” Marcos said.

Article continues after this advertisement

“This has been a huge waste which could have been benefiting the people of Aurora by now,” he added. (PNA)

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: APECO, Aurora

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.