Yellow alert up in Luzon grid on Monday

MANILA, Philippines — National Grid Corporation of the Philippines (NGCP) has placed the Luzon grid under yellow alert for several hours on Monday, as 16 power plants are unavailable.

The grid operator explained, “a yellow alert is issued when the operating margin is insufficient to meet the transmission grid’s contingency requirement.”

READ: Luzon grid under yellow alert on Friday, says NGCP

In its latest advisory, the NGCP said it had raised the yellow alert in Luzon from 2 p.m. to 4 p.m. and 7 p.m. to 10 p.m.

Below are the factors that contributed to the raising of the yellow alert:

According to the grid operator, 2,692.8 megawatts are unavailable in the region. It added, “two plants have been on forced outage since 2023, two between January and March 2024, 12 power plants between April and May 2024; while six are running on derated capacities.”

Meanwhile, NGCP said Visayas and Mindanao grids “are under normal condition.”