National Grid Corp. of the Philippines (NGCP) has secured regulators’ green light for its proposed P9.7-billion Taguig Extra High-Voltage (EHV) Substation Project, which is intended to accommodate supply inflows from any new power plants.

The Energy Regulatory Commission (ERC) approved NGCP’s application for permission to build the project that would serve as another drawdown substation to decongest the San Jose EHV Substation and provide higher level of reliability to the Luzon Grid system.

ADVERTISEMENT

The San Jose EHV Substation is the chief merging point of bulk electricity supply coming from coal-fired power plants in Masinloc, Zambales, and Sual, Pangasinan, in the north of Metro Manila and well as power plants in Quezon in the south.

“The approval of the NGCP’s Taguig Extra High-Voltage (EHV) substation project will address the growing power demand and power import in Metro Manila,” ERC Chair Agnes Devanadera said in a statement.

FEATURED STORIES

“Additional capacities that will be injected into the transmission network by new power generators will soon be accommodated through this project, which will mean a sustainable and reliable supply of power” Devanadera said.

Apart from the decongestion of the San Jose EHV Substation, the 500-kilovolt Taguig EHV Substation will also ease traffic in the existing 230 kV single-circuit line from Quezon province to Muntinlupa City during emergency situations such as grid failure.

Taguig EHV will also  address the severe under voltage in the 230-kV substations within Metro Manila, caused by the single-circuit configuration and heavy loading condition of the Quezon-Doña Imelda-Paco-Muntinlupa 230 kV Transmission Line.

In addition, the Taguig EHV Substation will complement the plan of linking the new drawdown substation to Taytay 230-kV Substation, since it will make an additional 230 kV transmission line link to the said Taytay Substation.

According to NGCP, Taguig EHV is one of its major transmission network developments for Metro Manila which are meant ensure that the power requirements of the country’s load center will be adequately and reliably served in the long term.

ADVERTISEMENT
Subscribe to Inquirer Business Newsletter
Read Next
EDITORS' PICK
MOST READ
Don't miss out on the latest news and information.
View comments

Subscribe to INQUIRER PLUS to get access to The Philippine Daily Inquirer & other 70+ titles, share up to 5 gadgets, listen to the news, download as early as 4am & share articles on social media. Call 896 6000.

TAGS: National Grid Corp. of the Philippines, NGCP, Taguig
For feedback, complaints, or inquiries, contact us.


© Copyright 1997-2020 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.