Transco sale of grid assets breaches P4B mark | Inquirer Business

Transco sale of grid assets breaches P4B mark

Since 2004, state firm sealed 83 deals
By: - Reporter / @amyremoINQ
/ 09:49 PM October 03, 2011

MANILA, Philippines—State-run National Transmission Corp. (Transco) has sold P4.08 billion worth of subtransmission assets to qualified power distribution utilities, since it began its privatization program in 2004.

As of April 30 this year, Transco has signed 83 sale contracts with 66 distribution utilities, electric cooperatives (ECs) or consortia, according to the 18th Status Report on Electric Power Industry Reform Act (Epira) Implementation.

Assets that were sold included an aggregate length of about 3,323 circuit-kilometers (ckm) of subtransmission lines and 30,200 subtransmission structures.

Article continues after this advertisement

Of the 83 sale contracts, 36 accounted for an aggregate sales price of P1.88 billion and which had been approved by the Energy Regulatory Commission (ERC). The rest of the sale contracts, however, are still up for ERC filing, evaluation and approval.

FEATURED STORIES

The Epira implementation report detailed how Transco managed to extend concessional financing to electric cooperatives by entering into lease purchase agreements worth P2.9 billion.

The deals involved sale contracts with 50 ECs/consortia.

Article continues after this advertisement

Under the Epira, subtransmission assets will be operated and maintained by Transco until their disposal to qualified distribution utilities (DUs). These utilities will take over the responsibility of operating, maintaining, upgrading and expanding the grid assets.

Article continues after this advertisement

In cases where more than one distribution utility is connected to a transmission line, there is a need for the connected and qualified utilities to form a consortium to buy and operate the asset.

Article continues after this advertisement

Transco’s subtransmission assets are made up of about 6,200 circuit-kilometers, comprising 69 kilovolt transmission lines and 1,600 megavolt amperes of substation capacity.

Estimated cost of these assets is about P7.6 billion based on 2007 net book values.

Article continues after this advertisement

“The transfer of ownership and control of the subtransmission assets will enable distribution utilities to expand their operations, become more efficient, serve more customers and improve service,” Transco had said.

“National Grid Corp. of the Philippines (NGCP) would be able to focus on its core function—managing the operation and maintenance of high-voltage transmission system. Thus, the electricity consumers become the ultimate beneficiaries of Transco’s divestment program,” Transco added.

NGCP, which took over the Transco concession in January 2009, is the operator of the country’s electricity superhighway.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

It has committed to ensure the safety, reliability and efficiency of the national power grid.

TAGS: electricity production and distribution, Energy, Philippines, Privatization, Transco

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.