MPIC starting Calax ahead of schedule | Inquirer Business

MPIC starting Calax ahead of schedule

/ 12:28 AM December 30, 2016

Infrastructure giant Metro Pacific Investments Corp. plans to start construction of the 45.5-kilometer Cavite Laguna Expressway ahead of schedule.

According to an indicative timeline from Metro Pacific, the group plans to start building the toll road in the first quarter of 2017 for completion by the end of 2018. Under the original schedule, construction would have started July 2017, with completion by the end of June 2019.

There were still certain “post-construction” activities that were slated. That meant the toll road’s start of operations would be on Jan. 1, 2020, six months ahead of the original schedule of July 31.

Article continues after this advertisement

The project, also called the Calax, was among the public-private partnership deals auctioned off under the Aquino administration. It was bagged by Metro Pacific unit MPCala Holdings in 2015.

FEATURED STORIES

The toll road aims to provide another link between Metro Manila and progressive provinces south of the capital district.

MPCala Holdings was awarded the project last month after its offer of P27.3 billion edged out sole rival San Miguel Corp., which offered P22.2 billion.

Article continues after this advertisement

Both companies offered premium bids, meaning these come on top of the toll road’s estimated cost of P35.4 billion. The government had set at P20.1 billion floor premium bid for Calax for the second round of bidding held after the first round failed.

Article continues after this advertisement

The Calax auction process was marked by high drama during its initial bidding round in 2014, when SMC was disqualified due to a typographical error. That disqualification was later reversed by President Aquino, who also ordered the rebid that took place in 2015.

Article continues after this advertisement

Metro Pacific subsidiary Metro Pacific Tollways operates the 14-km Cavite Expressway in southern Metro Manila apart from the 94-km North Luzon Expressway and 94-km Subic-Clark-Tarlac Expressway (SCTEx).

It is also seeking to build an elevated connector road cutting through Metro Manila that would link NLEx to SMC’s South Luzon Expressway.

Article continues after this advertisement

The Calax will be four-lane expressway that starts at the Cavitex toll gate in Kawit, Cavite, and ends at the SLEx-Mamplasan Interchange in Biñan, Laguna.

Tollways remained a significant contributor to the bottom line of Metro Pacific, which is involved in power and water distribution, railways and hospital operations.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Calax, Cavite-Laguna Expressway, Infrastructure, Metro Pacific Investments Corp., MPIC, SCTEx, Subic-Clark-Tarlac Expressway

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.