11 groups vie for P35-B road project

Cavite-Laguna expressway bidding in December
/ 10:30 PM July 30, 2013

Cavite-Laguna Expressway Route Map https://www.dpwh.gov.ph

The big-ticket Cavite-Laguna Expressway public-private partnership (PPP) project has drawn the interest of at least 11 firms, which have purchased prequalification documents released by the Department of Public Works and Highways.

A statement from the PPP Center said the firms included San Miguel Corp., AC Infrastructure Holdings Corp. of Ayala Corp., Makati Development Corp. of Ayala Land Inc., Metro Pacific Tollways Development Corp. of Metro Pacific Investments Corp. and Aboitizland Inc. of Aboitiz Equity Ventures Inc.

Article continues after this advertisement

Also bidding for the toll road are Megawide Engineering Excellence of Megawide Construction Corp., Korea Expressway Corp., Malaysian-backed Alloy MTD Philippines Inc., Macquarie Infrastructure Holdings (Philippines) Pte. Ltd., Leighton Contractors (Philippines) Inc. and Egis Projects Developer of Infrastructure and Service.

FEATURED STORIES

The Cavite-Laguna Expressway is the third project of the DPWH under the PPP program and its biggest so far with an estimated cost of P35.42 billion for the four-lane, 47-kilometer expressway.

The project will start from the Manila-Cavite expressway in Kawit, Cavite, and end at the South Luzon Expressway-Mamplasan Interchange in Biñan, Laguna. When constructed, the Cavite-Laguna Expressway will decongest traffic along the Cavite-Laguna road network and reduce the travel time to and from Metro Manila.

Article continues after this advertisement

The prospective bidders were given until Sept. 23 to submit their prequalification requirements.

Article continues after this advertisement

The DPWH recently restructured the toll road into a “pure” PPP deal, which means the private sector will be responsible for the financing, design, construction, operation and maintenance of the entire project.

Article continues after this advertisement

Based on the original structure, a private group would operate the entire toll road but it would build only the 28.9-km stretch from Kawit to Aguinaldo Highway in Cavite. The government was to tap overseas development assistance (ODA) funds to build the remaining 18.1-km stretch.

Public Works Secretary Rogelio Singson said he expected the actual bidding to take place in December this year and the contract would likely be awarded to the winning bidder by January 2014.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: bidding, Business, Cavite-Laguna expressway project, public-private partnership

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.