Rules for foreign-assisted projects eased

MANILA, Philippines — The Department of Budget and Management (DBM) is allowing government agencies to program counterpart funding for foreign-assisted projects (FAPs) even before the loan agreement is finalized, under new guidelines aimed at speeding up implementation of priority projects.
Under National Budget Circular No. 581-A, the DBM said the new guidelines supplement those issued in December 2020 on the implementation of FAPs.
READ: Gov’t infra spending remains sluggish
These seek to address bottlenecks that have delayed FAPs, including problems involving site availability, right-of-way acquisition, procurement, funding flows, government and lender approvals, as well as project design and technical specifications.
“As the Philippine government accelerates the implementation of priority infrastructure and other socioeconomic programs, it is imperative to clarify and streamline key processes, particularly for the implementation of FAPs which were found to have been either delayed or with lapsed implementation period,” the DBM said.
Counterpart funding
One of the new rules allows an approved FAP to be included in the proposed national budget even if its foreign loan agreement has yet to be finalized.
The DBM said the government’s counterpart funding may already be included in the National Expenditure Program (NEP) as long as the project has been approved by the Investment Coordination Committee Cabinet Committee or the Economy and Development Council.
This means agencies can already set aside funding for the Philippine government’s share of FAP while waiting for the corresponding foreign loan to be finalized.
The DBM said the counterpart funding should be prioritized for activities needed to prepare the project for implementation, including detailed engineering, feasibility studies, right-of-way acquisition and resettlement, procurement and preparatory civil works.
READ: Gov’t ramps up infrastructure spending to revive economy, Palace says
The government counterpart may also cover personnel and operating costs, value-added tax, customs duties and capital outlays related to the project.
According to the DBM, the new guidelines are could help projects move more smoothly toward implementation and support the government’s efforts to bring the economy back to a higher growth trajectory.
The Marcos administration is targeting a 5-percent to 6-percent economic growth in 2027. In the first nine months of 2026, the economy has only grown 2.5 percent amid a continued slump in infrastructure spending and weak household consumption. INQ