MANILA, Philippines — The National Grid Corp. of the Philippines (NGCP) is seeking the withdrawal of two government circulars aimed at accelerating power project integration, saying these violate its exclusive mandate over the country’s transmission network.

In a position paper, the local market’s sole grid operator expressed its “vehement opposition” to the circulars released by the Department of Energy (DOE).

READ: CERA backs return of transmission planning to gov’t

Article continues after this advertisement

One of the Department Circulars (DC), DC No. 2026-01-0001, that raised issues included allowing generation companies (gencos) to finance and construct associated transmission projects.

FEATURED STORIES

NGCP likewise questioned a policy guideline under DC No. 2026-02-0007 enabling the National Transmission Corp. (Transco) to do the same. Still, it entails even wider coverage, as it includes transmission lines and facilities crucial to the energy transition.

The group maintained that the two department circulars were “clear in their intent to violate” the provisions of the Electric Power Industry Reform Act (Epira) of 2001 (Republic Act No. 9136) and RA No. 9511, which grants the NGCP a 50-year franchise to construct, operate, and maintain the transmission superhighway.

In the genco circular, NGCP stated that gencos can only develop and own or operate dedicated point-to-point limited transmission facilities. Allowing them to build associated transmission projects “is beyond the scope provided in the Epira,” it said.

It added that a provision of the circular tasks Transco with reviewing and ensuring that the Transmission Development Plan (TDP) supports the committed power plants.

Article continues after this advertisement

Contract breach cited

Moreover, NGCP said this violates its concession agreement, pointing out that it has the “exclusive right” to prepare the TDP. While the Energy Regulatory Commission (ERC) and the DOE can approve or reject particular projects as well as review the plan, Transco has “no such power.”

“Transco no longer has the statutory authority to perform transmission-related functions… Given that the Epira already divested Transco of its transmission functions, the DOE has no authority to return any such power or function to Transco,” it said.

Article continues after this advertisement

“The violation of NGCP’s rights is made more odious by the fact that Transco is 100 percent owned by the state, and the draft circular is from the DOE whose secretary sits on the Transco board,” the company said.

READ: Solon urges DOE: Stop allowing firms to build power plants anywhere

In addition, NGCP grid operator also claimed the circulars blamed only delays in implementing the TDP and the lack of transmission lines, without considering external factors affecting project deployment.

Consequently, the setbacks barring NGCP from pursuing the projects on schedule include delays in the release of ERC’s approval, land acquisition woes, and lengthy permitting processes in local government units.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

It also added that the relevant authorities must address any gaps in the transmission development by coordinating with the NGCP and ERC. /pai

TAGS: Department of Energy (DOE), National Grid Corp. of the Philippines (NGCP), transmission development plan

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.


© Copyright 1997-2026 INQUIRER.net | All Rights Reserved