P5-T investment needed to develop 25 GW hydropower

MANILA, Philippines — Expanding the country’s hydropower capability with an additional 25 gigawatts will require about P5 trillion in new investments, an energy official said Thursday.
According to Ariel Fronda, division chief of the DOE’s Hydropower & Ocean Energy Management Division, activating one megawatt from hydropower would cost about P200 million.
READ: The inverse relationship between solar and hydro power generation
Speaking to reporters on the sidelines of Aboitiz Power 101 in Laguna, Fronda said the country, particularly Luzon and Mindanao, has massive hydropower potential.
However, many areas remain untapped because building hydropower facilities requires hefty upfront capital.
As the government implements policies to support renewable energy expansion, including the green energy auction program (GEAP), Fronda hoped for more aggressive private-sector participation, including investment in storage facilities.
During the height of the Middle East war, disruptions in energy flows in the global market highlighted the need for a stronger power system.
“We are expanding our renewable energy portfolio responding to growing electricity demand, and strengthening energy security in an environment shaped by fuel price volatility, climate risks, and the changing operating requirements of our power system,” he said.
“These developments require us not only to build more generating facilities, but also to develop the flexibility, storage, and supporting infrastructure that will allow the entire power system to operate reliably,” the DOE official added.
Fronda particularly noted the role of hydropower plants with storage systems in supporting the integration of variable renewable energy.
Variable renewable energy includes wind and solar, as the power they generate depends on environmental conditions.
“Pumped storage facilities can absorb surplus or lower-cost electricity for later use. This can reduce the need to curtail renewable generation and help shift available energy toward hours when it is more valuable to the system,” he said.
The Philippines has only one pumped storage facility: the Kalayaan Pumped Storage Hydroelectric Power Plant, managed by energy giant Aboitiz Power.
Fronda said that the facility could help offset reduced generation from conventional hydropower plants, such as run-of-river and impounding facilities, during El Niño.
READ: First Gen banking on hydro power plants
As of the end of 2025, hydropower accounted for 12 percent of the total installed power generation capacity.
Many companies plan to launch more hydropower projects by 2028. /pai