NGCP to complete 7 major projects in 2026
Worth a total of P18.5B

NGCP to complete 7 major projects in 2026

/ 02:20 AM February 13, 2026
NGCP to complete 7 major projects in 2026
A facility of the National Grid Corp. of the Philippines. (PNA photo by Avito Dalan)

MANILA, Philippines — The National Grid Corp. of the Philippines (NGCP), which operates the country’s electricity grid system, expects to finish seven transmission assets worth P18.5 billion this year.

NGCP said these projects include the P8.1-billion 500/230 kilovolt (kV) Substation Stage 1 or the Tuy-Dasmariñas 500kV transmission line component. This is intended to cater to a coal-fired power plant as well as boost the dispatch of generation capacity in Batangas province.

Supporting higher power demand in the Boracay Island and Caticlan area, NGCP is set to energize the P4.2-billion Nabas-Caticlan-Boracay 138kV transmission line.

Article continues after this advertisement

READ: NGCP gets green light for 2 projects worth P32 billion

FEATURED STORIES

Its P2.4-billion Tuguegarao-Lal-lo 230 kV transmission is also poised for completion. This would provide relief to the anticipated load growth in the northern part of Cagayan province.

Visayas projects

NGCP is also beefing up grid reliability in Southern Negros with the P1.9-billion Amlan-Dumaguete 138kV transmission line.

The firm likewise seeks to address the overloading problem during outage through the completion of the P1.02-billion Stage 2 of the Visayas Substation Reliability project.

The P757.98-million Tacurong-Kalamansig 69kV transmission line and the relocation of steel poles along the Hermosa-Duhat 230kV transmission line. This costs P123.84 million and also expected to be completed within the year.

Article continues after this advertisement

READ: NGCP: Transmission rates up in February 2026 bills

“We take our obligations under our franchise and concession agreement seriously. Despite continuing challenges in right-of-way and permitting, we remain committed to the work ahead, and are optimistic in completing these projects within the year,” NGCP assistant vice president Cynthia Alabanza said in a media briefing on Thursday.

Article continues after this advertisement

Alabanza also sought support from the national and local agencies for the swift release of permits.

Their help “is vital to ensuring unhampered project implementation,” she said. INQ

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: electricity grid, National Grid Corp. of the Philippines (NGCP), transmission facilities

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.


© Copyright 1997-2026 INQUIRER.net | All Rights Reserved