MANILA, Philippines — The Luzon and Visayas grids are set to be placed on red alert on Thursday afternoon and evening, said National Grid Corporation of the Philippines (NGCP).

According to the NGCP advisory, the Luzon grid will be placed under red alert from 1 p.m. to p.m. and from 6 p.m. to 10 p.m.

It will also be placed under yellow alert in between those schedules, specifically, 12 noon to 1 p.m., 5 p.m. to 6 p.m. and 10 p.m. to 12 midnight.

Article continues after this advertisement

NGCP issues a red alert status when the power supply is insufficient to meet consumer demand and the transmission grid’s regulating requirement.

FEATURED STORIES

Meanwhile, a yellow alert is issued when the operating margin is insufficient to meet the transmission grid’s contingency requirement.

The current available capacity in the area is 13,531 megawatts, with the peak demand higher at 13,597 megawatts.

Article continues after this advertisement

READ: House probe sought on power grid’s frequent yellow, red alerts

Article continues after this advertisement

A total of 2,525.5 megawatts are currently unavailable to the grid as 18 power plants are currently on forced outage — three of which since 2023, four since between January and March 2024, and 11 since between April and May 2024.

Article continues after this advertisement

Three power plants are also currently running on derated capacities.

Visayas grid

The Visayas grid will also be placed under red alert, although for a shorter period, from 2 p.m. to 4 p.m. and 6 p.m. to 7 p.m.

Article continues after this advertisement

In between these schedules,  the grid will also be placed under yellow alert from 12 p.m. to 2 p.m., 4 p.m. to 6 p.m., and from 7 p.m. to 10 p.m.

The current available capacity in the Visayas is 2,588 megawatts, with the peak demand at 2,537 megawatts.

Twenty-one power plants are currently on forced outages — one since 2022, two since 2023, two between January and March 2024 and 16 between April and May 2024.

Three are currently running on derated capacities.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Due to this, 553.1 megawatts are currently unavailable to the grid.

TAGS: NGCP, red alert

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.