2 transport projects on track for ’22 completion ‍ | Inquirer Business

2 transport projects on track for ’22 completion ‍

By: - Reporter / @bendeveraINQ
/ 05:16 AM March 11, 2021

Two big-ticket infrastructure projects in Metro Manila aimed at enhancing the mobility of commuters and pedestrians alike have been progressing en route to starting their operations next year, according to two multilateral lenders that extended the loans to finance their implementation.

In a report, the Washington-based World Bank said the Metro Manila Bus Rapid Transit (BRT) Line 1 “made progress in engaging with Quezon City and the City of Manila” such that “both LGUs (local government units) have expressed their strong support to the project.”

A World Bank loan is financing the P5.5-billion, 11.5-kilometer BRT lane traversing Quezon Avenue and España Boulevard to serve as many as 300,000 passengers daily once in operation by June 2022.

Article continues after this advertisement

To accelerate implementation, the Department of Transportation needs to secure a budget for 2021 to proceed with the procurement of key consultant services, it said.

FEATURED STORIES

The BRT will cut the travel time between the stations in Quezon Memorial Circle and Manila City Hall from two hours to only 43 minutes through a system of 167 high-quality buses.

Faster and safer

Like trains, BRT systems run on dedicated lanes, carrying big numbers of travelers faster and safer. But unlike trains that run on rails, BRTs use buses, making the system simpler and cheaper to construct, operate and maintain.

Article continues after this advertisement

In a separate report, the Manila-based Asian Development Bank (ADB) said procurement for the P8.5-billion Edsa Greenways Project was on track to build covered and elevated walkways in Balintawak, Cubao, Guadalupe and Taft to allow pedestrians and commuters to hop from one public transport to another safely and seamlessly along Metro Manila’s main and traffic-congested thoroughfare.

Article continues after this advertisement

Construction goods and works for the Balintawak and Cubao walkways worth $71 million will undergo open competitive bidding as a package during the first half of 2021, just like the Guadalupe and Taft portions amounting to a combined $50.3 million.

The ADB in December last year green-lit the $123-million loan for its host-country’s Edsa Greenways, under which the Department of Transportation will build and rehabilitate a total of five kilometers of five-meter wide walkways near four Light Rail Transit and Metro Rail Transit stations.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: infrastructure projects, Metro Manila Bus Rapid Transit (BRT) Line 1

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.