COVID-19 ECQ delays WB-funded infra projects

By: - Reporter / @bendeveraINQ
/ 04:12 AM June 01, 2020

The enhanced community quarantine (ECQ) imposed in Luzon and other areas with high COVID-19 cases since mid-March has delayed the implementation of big-ticket infrastructure projects financed by the World Bank, such that the government will seek extension for some loans.

In the case of the Metro Manila flood management project it cofinanced with Beijing-based Asian Infrastructure Investment Bank (AIIB), the World Bank reported in May that “modernization of one pumping station, Balut, progressed well until the ECQ.”

The project being implemented by the Department of Public Works and Highways (DPWH), the Department of Finance and Metro Manila Development Authority (MMDA) was completing its second year of implementation, it noted.

ADVERTISEMENT

“All other project activities were suspended [during the ECQ]. The DPWH, MMDA and the World Bank team are working on a restart of project activities as soon as practical after the ECQ,” the lender said.

FEATURED STORIES

In 2017, the World Bank and the AIIB approved their respective loans of $207.6 million each, while the remaining $84.7 million for the $500-million project was shelled out by the national government.

This flood control project was aimed for completion in 2024.

In the case of the Cebu bus rapid transit (BRT), the World Bank said in a separate report that the project had shown significant progress.

“However, the enforcement of the ECQ … has slowed down the implementation of critical project activities,” it said.

Amid the delays, the World Bank said given that the current loan closing date is in June 2021, it was expecting the Department of Transportation to initiate the process for loan extension soon.

In 2014, the World Bank approved a $141-million loan for the project to augment the $87.5 million earmarked by the government for the project.

ADVERTISEMENT

The 23-kilometer Cebu BRT was originally targeted for completion in October this year but project implementation had been delayed. INQ

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

For more news about the novel coronavirus click here.
What you need to know about Coronavirus.
For more information on COVID-19, call the DOH Hotline: (02) 86517800 local 1149/1150.

The Inquirer Foundation supports our healthcare frontliners and is still accepting cash donations to be deposited at Banco de Oro (BDO) current account #007960018860 or donate through PayMaya using this link.

TAGS: Business, COVID-19, Infrastructure

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

We use cookies to ensure you get the best experience on our website. By continuing, you are agreeing to our use of cookies. To find out more, please click this link.