First Philippine Holdings to pursue power projects that will generate 280 MW | Inquirer Business

First Philippine Holdings to pursue power projects that will generate 280 MW

MANILA, Philippines — The Lopez-led First Philippine Holdings Corp. (FPH) plans to expand its power generation capacity by 280 megawatts in the next three to four years by mostly focusing on renewable energy.

FPH’s recurring earnings might decline this year by about a third compared to that of 2010, company president and chief operating officer Elpidio Ibanez told reporters after the company’s stockholders meeting.

Aside from the absence of one-time gains realized from the sale of shares in Manila Electric Co. in 2010, this year’s performance would be affected by foregone revenues as well as higher expenditures from the rehabilitation of geothermal power plants as well as the continuing suspension of a gas pipeline that previously leaked into a residential tower in Makati, he said.

Article continues after this advertisement

On power distribution, FPH intends to keep its remaining 6.6 percent stake in Meralco, FPH chair and chief executive officer Federico Lopez said. FPH had sold most of its stake to the First Pacific group.

FEATURED STORIES

“There’s no intention of selling. Meralco is doing very well under Manny Pangilinan,” Lopez said.

Richard Tantoco, president of the geothermal unit Energy Development Corp., said the group’s greenfield power projects would focus on geothermal and wind energy.

Article continues after this advertisement

The group’s power generation, through power holding firm First Gen Corp., has about 2,800 MWs, which will increase by another 130MW by the year’s end as BacMan geothermal power plant comes back on stream. At the same time, the group is drilling in new sectors within BacMan, scheduled for delivery to the national grid by 2014-2015.

Article continues after this advertisement

Meanwhile, a wind power project in Burgos, Ilocos Norte, is in the pipeline with a projected capacity of 85 to 100 MW. Tantoco said EDC was hoping to start this project, which would cost $280 million to $300 million, within the year.

Article continues after this advertisement

The 280-MW increase in capacity planned by 2014-2015 assumes that this wind project will move ahead while additional capacity in Bicol and Mindanao will progress as planned.

This capital, FPH’s group-wide capital spending is set at around P8.8 billion, consisting of around P6.8 billion for EDC’s expansion and another P2 billion for the solar wafer projects of the First Philec Solar Corp.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: Business, electricity production and distribution

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.