Neda: Groundbreaking of 34 ‘flagship’ infra projects set for 2018 | Inquirer Business

Neda: Groundbreaking of 34 ‘flagship’ infra projects set for 2018

By: - Reporter / @bendeveraINQ
/ 05:19 PM January 18, 2018

ROLANDO G. TUNGPALAN. PHOTO FROM NEDA.GOV.PH

The government will break ground for 34 or almost half of the 75 “flagship” infrastructure projects under the Duterte administration’s ambitious “Build, Build, Build” program, the state planning agency National Economic and Development Authority said Thursday.

In a forum, Neda Undersecretary Rolando G. Tungalan said one project already broke ground before 2017, while 15 were rolled out last year.

ADVERTISEMENT

Next year, 10 flagship projects will be launched, on top of four planned for rollout in 2020.

FEATURED STORIES

The groundbreaking schedules for 11 projects were yet to be determined.

As of Jan. 15, 66 of the 75 flagship projects were estimated to cost a total of P2.289 trillion, Tungpalan said.

Among the big-ticket projects to be rolled out this year included 12 bridges that will cross the Pasig River, Marikina River as well as Manggahan Floodway.

These bridges to be constructed by the Department of Public Works and Highways starting this year until 2022 will “improve road transport network capacity and efficiency in Metro Manila” as well as “alleviate traffic congestion,” Tungpalan said.

The DPWH will also roll out the P4.86-billion Panguil Bay Bridge project that will connect Tangub City in Misamis Occidental and Tubod, Lanao del Norte, for completion in 2021.

The Department of Transportation, meanwhile, will implement the P35.26-billion, 102-kilometer Mindanao Rail Project (Phase 1) that will connect Tagum, Davao City and Digos in Region 11, which is expected to be completed by 2022.

ADVERTISEMENT

The DOTr will also start this year work on the P211.43-billion Philippine National Railway North 2 project, the 69.5-kilometer extension of the PNR North 1 from Malolos, Bulacan to Clark International Airport and the sprawling Clark Green City, eyed for completion in 2024.

Also for rollout in 2018 is the DOTr’s P175.3-billion PNR South Long-Haul project, a 639-kilometer rail consisting of the following lines: 406-kilometer Los Baños to Legazpi; 117-kilometer Legazpi to Matnog; 58-kilometer Calamba to Batangas; and 58-kilometer Manila to Los Baños.

Tungpalan said the PNR South Long-Haul railway will be financed by China.

Next year, the DOTr will begin implementation of the P355.59-billion Metro Manila Subway Project (Phase 1), a 25.3-kilometer underground rail that will connect Quezon City and Taguig City as well as extend to the Ninoy Aquino International Airport.

The subway, to be financed by Japan, would be completed by 2027, Tungpalan said.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Under “Build, Build, Build,” the government plans to rollout 75 flagship, “game-changing” projects, with about half targeted to be finished within President Duterte’s term, alongside spending a total of up to P9 trillion on hard and modern infrastructure until 2022 to usher in “the golden age of infrastructure” after years of neglect. /je

TAGS: Build Build Build, groundbreaking, Infrastructure, National Economic Development Authority, NEDA, project