Meralco eyes power supply deals with JG Summit, other firms | Inquirer Business

Meralco eyes power supply deals with JG Summit, other firms

/ 11:35 PM January 18, 2015

MANILA Electric Co. is working on interconnection deals with owners of large-capacity power generation sets and with a state-owned hydroelectric power plant.

In its latest report on the Interruptible Load Program (ILP), the main coping mechanism for the power crisis in Luzon this summer, Meralco said there were prospects for interconnection with the JG Summit Group.

JG Summit has indicated exportable capacity of 19MW from the diesel-fed generator set in Calamba, Laguna and one in Pasig City. Meralco said the diesel engines in JG Summit’s facilities could either be used to de-load as in the ILP program or be directly connected to supply power to the power distribution network via a power purchase agreement.

Article continues after this advertisement

So far, 936.96MW of pledged and potential capacity has been listed under the ILP.

FEATURED STORIES

Another possible interconnection deal will  involve the 20-MW Botocan hydroelectric power plant of National Power Corp., whose assets are being managed by Power Sector Assets and Liabilities Management (PSALM) Corp. The Botocan facility, located in Laguna, is available with the recent restoration of the Caliraya-Botocan transmission line.

Botocan’s output may be the subject of a PPA or it may sell its output through the Wholesale Electricity Spot Market, the energy trading platform where Meralco may get its “uncontracted” electricity supply needs.

Article continues after this advertisement

Napocor, for its part, said its IPP contracts management department was able to successfully bid out and implement the restoration work for the Botocan-Kalayaan 115kV line last Aug. 27, 2013. Restoration work is reportedly done, enabling Napocor to transmit the 20MW capacity of the Botocan Hydroelectric Plant in Majayjay, Laguna to the Luzon grid. Botocan is part of the 728-MW Caliraya-Botocan-Kalayaan (CBK) hydropower plant complex, which is among the power assets PSALM wants to dispose of.

Article continues after this advertisement

A third prospect for interconnection is Millenium Energy Inc.’s 100-MW diesel power station in Navotas, possibly by March 2015.

Energy Secretary Carlos Jericho L. Petilla said Millenium was committed to supply Meralco’s network by summer and that talks were ongoing for the interconnection.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

TAGS: deal, JG Summit, Meralco, power, supply

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

© Copyright 1997-2024 INQUIRER.net | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies. Learn more here.